Timeline

This page details the main timeline for the project, with a list of key milestones.  The yearly timelines below are more detailed and list more detail around the project – this will be developed and updated as work progresses. 

If you would like to keep up to date with what’s happening, you can take a look at our newsletters – you can also sign up to our mailing list, so that you receive our monthly update direct to your inbox.

July - Oct 2012
Development of detailed construction programme in conjunction with ongoing design, traffic management planning and construction phasing.
Sept - Oct 2012
Series of public exhibition to explain works programme and construction phasing.
Oct 2012
Commencement of site works.
Jan - Mar 2013
Construction activity increases
Summer 2013
Retaining walls at Aller Park Road and St Luke’s Road completed
Winter 2013
Aller Culvert completed
Spring 2014
North ramp completed
Summer 2014
Maddacombe Road and Yon Street bridges completed
Spring 2015
Aller Railway Tunnel completed South Ramp completed Flyover bridge completed
Autumn 2015
Edginswell Junction opens
December 2015
Projected completed